Skylights (RFP) — CANCELLED

The Request For Proposal for the Transbay Transit Center TG08.3 – Skylights Trade Package has been cancelled. The scope of the TG08.3 – Skylights Trade Package will be incorporated into a new TG08.11 – Glass Curtain Walls and Skylights Trade Package. The TG08.11 – Glass Curtain Walls and Skylights Trade Package is scheduled to be issued in November, 2014.

REQUEST FOR PROPOSALS: SKYLIGHTS CONSTRUCTION SERVICES PACKAGE

Webcor/Obayashi Joint Venture seeks responses to a Request for Proposals (RFP) from Trade Subcontractors interested in submitting a proposal for TG08.3 – Skylights Construction Services trade package on the current for the Transbay Transit Center (TTC) Project located in San Francisco, California.

Webcor/Obayashi Joint Venture seeks Trade Subcontractors that have significant experience in design, fabrication and installation of metal framed glass skylights on complex projects which require significant coordination with adjacent properties and traffic relocation located in an urban environment; including the engineering, coordination, procurement and complete installation of their respective systems in the following trade:

TG08.3 Skylights

Webcor/Obayashi Joint Venture and the TJPA are seeking are seeking qualified firms to provide Design/Build services under TG08.3 – Skylights in accordance with the Contract Documents and Field Direction. The Trade Subcontractor is recognized as a licensed professional Trade Subcontractor and is required to provide a complete scope of work, including any items not shown in the Contract Documents which are typically included in this scope of work.

A Pre-Proposal Conference for Trade Subcontractors interested in submitting proposals was held on Thursday, August 21, 2014, at 2:00 pm, at Webcor/Obayashi Joint Venture’s project office at 175 Beale Street, San Francisco, CA 94105. Attendance at the pre-proposal conference was optional but highly encouraged.
Pre-Proposal Conference Presentation | Pre-Proposal Conference Sign-In Sheets

Each Proposer shall submit sealed proposals to the Webcor/Obayashi Joint Venture offices, located at 175 Beale Street, San Francisco, CA 94105-1801 by 2:00 p.m. Pacific time on Thursday, November 13, 2014. No proposal will be accepted after 2:00 p.m. on the Proposal Due Date.

Webcor/Obayashi Joint Venture reserves the right to contact Proposers after Proposal submission for the purpose of clarifying a Proposal. This contact may include written questions, interviews, site visits, and/or a review of past performance. Webcor/Obayashi Joint Venture will not consider information received from or through a Proposer if the information materially alters the content of the Proposal or the type of goods and/or services the Proposer is offering to Webcor/Obayashi Joint Venture. An individual authorized to legally bind the Proposer shall sign responses to any request for clarification. Responses shall be submitted to Webcor/Obayashi Joint Venture within the time specified in the Webcor/Obayashi Joint Venture’s request. Failure to comply with requests for additional information may result in rejection of the Proposal.

No proposal is accepted and no contract in excess of $400,000 is awarded by the TJPA until the TJPA Board of Directors approves the award. All contract awards are subject to certification by the TJPA Chief Financial Officer as to the availability of funds. If Webcor/Obayashi Joint Venture chooses to recommend any of Trade Package: TG08.3 Skylights Package contract work to the TJPA for its approval, the Trade Subcontractor will be asked to comply with all TJPA contract requirements. Trade Subcontractors will be required to meet a Small Business Enterprise (SBE) utilization goal. An SBE is defined in the Transbay Joint Powers Authority (TJPA) Board Policy No. 15, Small Business Enterprise Program. The SBE utilization goal on this contract is 5%. Trade Subcontractors will be required to sign a letter of assent to the Transbay Transit Center Project Labor Agreement. Minimum wage rates for this Project must comply with the current General Prevailing Wage as determined by the State Department of Industrial Relations. Minimum wage rates other than those applicable to General Prevailing Wage must comply with San Francisco Administrative Code, Chapter 12P, Minimum Compensation Ordinance. The Specifications include liquidated damages. Contract will be on a Lump Sum basis. Progressive payments will be made. More detail on each of these items is included in the RFP documents.

Bid Plans, Specifications, and reference documents for the Project may contain protected information pertaining to sensitive, financial, commercial, or proprietary business information and/or the security of the Project. Such protected information is classified as Confidential Information, Sensitive Security Information (SSI) or Protected Critical Infrastructure Information (PCII).

Bid Plans, Specifications, and reference documents containing protected information will be made available to Bidders on the TJPA’s secure website after they have signed and returned a completed Non-Disclosure Agreement (NDA) to the Transbay Joint Powers Authority (TJPA). In addition to submitting signed NDAs for each individual requesting access to protected information, each bidding firm must submit to the TJPA a list of all Designated Individuals in its organization who require access to protected information. Refer to the NDA Instructions, linked below, for detailed information and instructions.

Bid Plans and Specifications that do not contain protected information may be purchased via ARC – Northern California PlanWell, (415) 495-8700. Other package documents, including the Project Bidding Manual, are posted below.

Use the following links to download the NDA Instructions, the NDA form, and the NDA attachment; an Excel template for the NDA Designated Individuals list; and a diagram showing how Bidders access SSI. Use the “upload” button below to submit signed NDAs and the completed NDA Designated Individuals list.

NDA Downloads No. of Files: 3
Click titles below to download
NDA Instructions, NDA Form, NDA Attachment Form 136KB .pdf Posted 8/6/14
NDA List of Designated Individuals 73KB .pdf Posted 8/6/14
How-Bidders-Access-SSI_1310252 65KB .pdf Posted 8/6/14

Download Documents (Note: Don’t forget to Register to be alerted when changes and new documents are added)
Document (Click to Download) File Size & Type Date Posted
Editable QPD Form 28 KB .pdf 8/1/14
Preconstruction RFI’s Update (Dated October 7, 2014) 222KB .pdf Posted 10/7/14
TG08.3 Pre-Proposal Conference Questions & Answers 26KB .pdf Posted 9/8/14
Addendum #2 Cover Letter TG08.3 (RFP TG08.3 – CANCELLED) 91KB .pdf Posted 11/4/14
Addendum #1 Cover Letter TG08.3 (Documents noted below as Addendum #1 are updated in this Addendum; revised plans/specs available from ARC-Northern California PlanWell) 176KB .pdf Posted 9/16/14
Cover Letter 184 KB .pdf 8/1/14
RFP TG08.3 Exhibit A (Addendum #1; Rev. A) 11,994 KB .pdf 9/16/14
Exhibits B – S, U & W 20,173 KB .pdf 8/1/14
Exhibit F(Addendum #1) 685 KB .pdf 9/16/14
Exhibit I (Addendum #1) 81 KB .pdf 9/16/14
Long Form Subcontract (Addendum #1) 500 KB .pdf 9/16/14
Request for Proposals Manual (Addendum #1; Rev 17) 754 KB .pdf 9/16/14
TG08.3 Advertisement 83 KB .pdf 8/1/14
Package Timeline
Proposal Package Issued Friday, August 1, 2014
Pre-Proposal Conference Thursday, August 21, 2014, 2:00 p.m.
Deadline for Submission of Questions Tuesday, October 14, 2014, 2:00 p.m.
Pre-bid Request for Substitution Tuesday, October 14, 2014, 2:00 p.m.
Proposal Packages Due Thursday, November 13, 2014, 2:00 p.m.
Proposers Notified of Interviews Thursday, November 20, 2014
Finalist Interviews/Submissions December 1 – 5, 2014
Negotiations December 8 – 18, 2014
Notification of Intention to Award Contract December 19, 2014
Protest Period December 22, 2014, 2:00 P.M. – December 30, 2014, 2:00 p.m.
TJPA Board Vote to Approve the Contract Award January 8, 2015 (January 2015 TJPA Board meeting)

For notification of updates, contractors are encouraged to register on the TJPA’s website. However, all contractors are solely responsible for ensuring the receipt of any and all addenda, question and answers on Proposals, and RFI Cover Letters; contractors are responsible to check the website before submitting their Proposals to ensure receipt of all documents, and to ensure their proposals respond to any such documents.