REQUEST FOR QUALIFICATIONS: DOORS / FRAMES / HARDWARE CONSTRUCTION SERVICES PACKAGE
Webcor/Obayashi Joint Venture issued a Request for Qualifications (RFQ) from Trade Subcontractors interested in bidding the Doors/Frames/Hardware on the contract for the Transbay Transit Center (TTC) Project located in San Francisco, California, on July 10, 2014. The RFQ sought Trade Subcontractors with significant experience with doors, frames, hardware, punched windows, and low voltage wiring on complex projects. Also included are engineering, coordination, procurement and complete installation of the respective systems in the following trade:
TG16.6: Doors/Frames/Hardware
Trade Subcontractors will be required to have second-tier subcontractors in order to meet the Transbay Joint Powers Authority’s (TJPA’s) Small Business Enterprise (SBE) participation goals. Second-tier subcontractors did not need to respond to this RFQ, regardless of SBE status. Visit Doing Business with the TJPA for a link to the Small Business Enterprise (SBE) program as well as web-links to the programs that the TJPA accepts certifications from in its SBE Program.
Under the RFQ process, the following firms were pre-qualified to bid the scope of work when contract documents are released:
- Boyett Construction, Inc.
- Corbin Building, Inc.
- ISEC. Incorporated
- Minton Door Company
- Rubecon Builders Inc.
- Swinerton Builders
Pre-Qualified Bidders Contact List for TG16.6 (as of September 11, 2014)
Contract documents, including plans and specifications, for the project are anticipated to be available for bidding in 2015. If Webcor/Obayashi Joint Venture chooses to recommend any of TG16.6 Doors/Frames/Hardware package contract work to the TJPA for its approval, the Trade Subcontractor will be asked to comply with all TJPA contract requirements, including signing a letter of assent to the Transbay Transit Center Project Labor Agreement (PLA) and certifying compliance with federal Buy America regulations. See our Project Labor Agreement webpage for PLA and Small and Disadvantaged Business Enterprise Frequently Asked Questions.
Download Documents (Note: Don’t forget to Register to be alerted when changes and new documents are added) | ||
Document (Click to Download) | File Size & Type | Date Posted |
RFP Questions & Answers Set #1 TG16.6 | 11 KB .pdf | 8/6/14 |
Request for Qualifications TG16.6: Doors/Frames/Hardware | 456 KB .pdf | 7/10/14 |
TG16.6: Doors/Frames/Hardware Advertisement | 11 KB .pdf | 7/10/14 |
Key RFQ Dates | |
RFQ Issued | Thursday, July 10, 2014 |
Deadline for Submission of Questions | Thursday, July 24, 2014, 2:00 p.m. |
RFQ Packages Due | Thursday, August 7, 2014, 2:00 p.m. |
Evaluate RFQ Packages | August 8 – August 20, 2014 |
Issue Notices to Qualified Trade Subcontractors | Thursday, August 21, 2014 |