Community Meeting – February 17, 2016

Community Meeting on Transbay Construction Activities

The Transbay Transit Center Project is progressing fast with Train Box Lid concrete complete up to Fremont Street. More headway is occuring on-site with welding and underground utility work as well. During the next month, bus ramp construction will increase with concrete pours and falsework activities. It is a busy time here at the Transbay Project!

Join us for a community meeting on Wednesday, February 17, 2016, to learn more about these activities and what’s in store in the coming months. This meeting will be held at 12 noon at the TJPA offices located at 201 Mission Street, Suite 2100. We appreciate you taking your lunch hour to learn about this innovative project, and welcome you to bring food or drinks to this meeting.

What:        Community Meeting: Transbay Construction Update

When:       Wednesday, February 17, 2016

Time:        12 noon

Where:     Transbay Joint Powers Authority

201 Mission Street, Suite 2100

San Francisco, CA 94105