Program Timeline
1907-1967
1967
Caltrans Begins Study on Future of Transbay Terminal
Caltrans begins study to determine future role of Transbay Terminal once Transbay BART service begins.
1959
Terminal Converted to Bus-Only Facility
The Transbay Terminal is converted to a bus-only facility when the Key System rail stops running on the lower deck of the Bay Bridge. AC Transit begins utilizing the Terminal deck and ramps, along with other local and long-distance bus carriers.
Photo Credit: San Francisco History Center, San Francisco Public Library.
1958
Final Key System Train Leaves the Terminal
Following World War II and the prevalence of the automobile, rail travel began to decrease. The final Key System train left the Terminal in 1958. The railway is removed from the lower deck of the Bay Bridge.
Photo courtesy of The Bay Bridge (Images of America) by Paul C. Trimble and John C. Alioto, Jr.
1941
‘Red Trains’ Cease Terminal Operation
Southern Pacific Railway “Red Trains” cease operation to the Transbay Terminal.
Photo courtesy of The Bay Bridge (Images of America) by Paul C. Trimble and John C. Alioto, Jr.
1939
Transbay Terminal Constructed
The Transbay Terminal is built in 1939 to accommodate rail service over the San Francisco-Oakland Bay Bridge. In its heyday, more than 26 million people used the Transbay Terminal each year.
Photo courtesy of The Bay Bridge (Images of America) by Paul C. Trimble and John C. Alioto, Jr.
1936
Bay Bridge Opens
In 1936, the San Francisco-Oakland Bay Bridge opens. The construction of railway facilities is delayed while a cost-sharing plan is debated among state toll bridge authority and private railways.
1933
Site Selected for Transbay Terminal Rail Services
A site is selected for the Transbay Terminal rail services in downtown San Francisco. The new site at First and Mission streets is selected because it is the closest option near the center of activity in downtown San Francisco and connects to the new Bay Bridge.
Photo courtesy of The Bay Bridge (Images of America) by Paul C. Trimble and John C. Alioto, Jr.
1930
Route for Bay Bridge Selected
The Hoover Commission selects Rincon Hill to Oakland Mole, via Yerba Buena Island, as a route for the Bay Bridge.
1912
Temporary Terminal Built at Third & Townsend
A temporary terminal constructed for Southern Pacific passenger service at Third & Townsend streets, to be completed in time for 1915 World’s Fair; plans are made to bring trains to a new terminal in downtown San Francisco, but are never realized.
1907
‘Bayshore Cut-Off’ Opens
The “Bayshore Cut-Off” opens, giving Southern Pacific trains a quick route into San Francisco.
1970′s & 80′s
1989
Loma Prieta Earthquake Damages Transbay Terminal
The Loma Prieta earthquake rocks San Francisco in 1989, damaging the Transbay Terminal and surrounding freeway ramps.
Caltrans’ Office of Structural Design completes designs for major revitalization of existing terminal, to bring the building up to current accessibility and life-safety codes.
1988
MTC Approves Resolution 1876
Metropolitan Transportation Commission approves Resolution 1876, calling extension of Caltrain to downtown San Francisco a top regional priority.
1983
Caltrans Develops Plans to Extend Railway to Transbay Terminal
Caltrans, as part of its responsibility for operating new Caltrain commuter service, develops plans to extend railway to Transbay Terminal.
1980
Caltrans Acquires Operation of Southern Pacific Service Between SF and SJ
Caltrans takes over responsibility for the operation of the century-old Southern Pacific commuter service between San Francisco and San Jose, renaming it “Caltrain.”
1978
SFBATTA Study Concludes
San Francisco Bay Area Transportation Terminal Authority (SFBATTA) study concludes; lowest-cost option is implemented, a minimal upgrade of the terminal.
1975
SFBATTA Established; San Francisco’s Railway terminal Moved to Fourth & Townsend
SFBATTA established to oversee operations and planning of the Transbay Terminal. San Francisco’s railway terminal is moved a block farther from downtown, to Fourth & Townsend streets, to make way for a freeway off-ramp that is never constructed.
1974
Transbay Transit Terminal Transportation Study Released
Transbay Transit Terminal Transportation Study released, calling for terminal with off-street facilities for all bus operators; peak capacity in new terminal would be 630 buses per hour, with direct ramps to Bay Bridge and US-101.
1972
Final Report is Issued, Favors Demolition of Existing Terminal
Final report is issued and favors demolition of existing terminal with construction of a new regional transportation center to serve both commuters and long-distance passengers plus three million square feet of private development in air rights above the terminal.
1990′s
1999
Proposition H Approved
Proposition H is overwhelmingly adopted by San Francisco voters, which makes it City law to extend Caltrain tracks to a new or rebuilt regional transit station on the site of the Transbay Terminal, and to pursue other improvements.
1998
Caltrain Proposes to Eliminate Eastern Ramp into Terminal
As part of seismic work to retrofit the Bay Bridge ramps, Caltrans proposes to eliminate the eastern ramp into the Transbay Terminal.
1997
Draft EIR for Downtown Extension Project Released
Draft EIS/EIR for the Caltrain San Francisco Downtown Extension Project released but never certified.
1995
Transit Terminal Decision Report Prepared
Transit Terminal Decision Report prepared, presenting three options for location of a new terminal.
1994
Final Report for Downtown Extension/Systems Upgrades Issued
The Caltrain San Francisco Downtown Extension/Systems Upgrades Final Report is issued. Options considered include surface operation of Caltrain into the South of Market Area (SOMA) all the way to Market Street.
1993
Study Released Suggesting Location for New Terminal
The San Francisco Planning Department releases a Transit Terminal Study suggesting a location for the new terminal.
1992
Mayor Frank Jordan Asks Caltrans to Consider Removing Terminal; PCJPB Acquires Caltrain Operations
Mayor Frank Jordan asks Caltrans to consider removing Transbay Terminal and replacing it with a smaller terminal.
Peninsula Corridor Joint Powers Board takes over Caltrain operations from Caltrans.
1991
PCJPB & MTC Study Alternatives to Bring Caltrain to Downtown SF
The Peninsula Corridor Joint Powers Board (PCJPB) and Metropolitan Transportation Commission (MTC) begin to study low-cost alternatives to bring Caltrain closer to downtown San Francisco.
1990
Administrative Draft of Caltrain Downtown Extension Released
The administrative Draft of Caltrain Downtown Extension is released. Alternatives considered include a six-track terminal underground behind the Transbay Terminal, and a three-level underground terminal beneath Second Street at Market Street. The study never progresses due to lack of a funding plan, but provides the basis for continued study of extending Caltrain into downtown San Francisco.
2000-2004
July 15, 2004
Final Environmental Impact Statement/Environmentatl Impact Report (FEIS/EIR) Certified
San Francisco Board of Supervisors certifies FEIS/EIR.
April 22, 2004
TJPA & PCJPB Certify FEIS/EIR
TJPA and Peninsula Corridor Joint Powers Board certify the FEIS/EIR and select a Locally Preferred Alternative (LPA) alignment into downtown San Francisco.
April 2004
AIA Awards Honor for Design for Development Plan
Design for Development Plan receives an Urban Design Award from the American Institute of Architects.
March 2004
Bay Area Voters Approve Regional Measure 2 Bridge Toll Increase
Regional Measure 2 bridge toll increase is approved by Bay Area voters and allocates $150 million in project funding.
February 2004
Engineering Design Services Contract for DTX Awarded
RFP issued for Engineering Design Services for the Caltrain Downtown extension (DTX) Project. Contract awarded to Parsons/ARUP/Jacobs Associates in December 2004.
2003
San Francisco Voters Pass Proposition K
San Francisco voters pass Proposition K, a half-cent sales tax extension for transportation, which earmarks $270 million for Transbay Terminal/Caltrain Downtown Extension Program as long as the project includes the extension of Caltrain. California Senate Bill 916 sets foundation for Regional Measure 2, the Regional Traffic Relief Plan.
July 2003
State Legislation Passes Requiring Affordable Housing, High-Speed Rail for Project
State legislation passes which requires 35 percent affordable housing in the new Transbay Redevelopment Area and that the new Transbay Terminal at First and Mission streets be designed to accommodate bus, Caltrain and high-speed rail.
March 2003
$9.3 Million in Funding Released for Planning & Preliminary Design
Selection of Locally Preferred Alternative (LPA) by the TJPA Board facilitates release of approximately $9.3 million in federal and regional funds to continue planning and preliminary design of the Transbay Terminal.
2002
Draft EIS/EIR Published
Draft EIS/EIR published and released for public review and comments followed by Public Hearings held by the San Francisco Redevelopment Agency.
September 2002
California Senate Bill 1856 Presented
California Senate Bill 1856 requires that initial segment of California High-Speed Rail connect San Francisco Transbay Terminal and Los Angeles Union Station.
December 2001
Transbay program Included in MTC Resolution 3434 & Regional Transportation Plan
The Transbay Program is included in the Metropolitan Transportation Commission’s Regional Transit Expansion Policy (MTC Resolution 3434) and the Regional Transportation Plan.
April 2001
Transbay Joint Powers Authority (TJPA) Created
City & County of San Francisco, AC Transit, and Peninsula Corridor Joint Powers Board enter into an agreement creating the Transbay Joint Powers Authority (TJPA), with a five-person Board of Directors.
March 2001
MTC’s Bay Crossing Study Begins
The Metropolitan Transportation Commission’s Bay Crossings Study begins to examine options for providing additional capacity across the bay. The study covers an area from San Francisco to Silicon Valley and includes all modes.
January 2001
Design Concept for New Transbay Terminal Published
Executive Committee of the Transbay Terminal Improvement Study Panel publishes design concept for new Transbay Terminal, an inter-modal bus and rail transit station to serve the Bay Area and the State. The plan also includes development of certain surrounding parcels and envisions a new transit-oriented neighborhood with retail, offices, and 3000 residential units.
2000
Environmental Review of the Project Begins.
The City & County of San Francisco and Peninsula Corridor Joint Powers Board execute a Memorandum of Understanding (MOU) to be co-lead agencies for the Caltrain extension project.
The Bay Area Toll Authority and the Transbay Terminal Improvement Study Panel select the preferred design for the new terminal: stacked configuration with Caltrain and high speed rail underground, joint use at ground level and on a mezzanine, two levels of bus bays and dedicated ramps connecting the bus decks to the Bay Bridge; the Plan is the result of a lengthy consensus-building design process that included needs of all operators.
2005-2009
December 10, 2008
Groundbreaking Ceremony at Temporary Terminal Site
A groundbreaking ceremony launches the first step in the Transbay Transit Center program – construction of the Temporary Terminal, the temporary facility that will serve bus passengers while the new landmark Transbay Transit Center is under construction.
2008
Construction of Temporary Terminal Begins
Construction of the Temporary Terminal begins in fall 2008. The temporary replacement bus facility will serve bus passengers while the new multi-modal Transbay Transit Center is under construction.
December 13, 2007
California Transportation Commission Approves Transfer of State Land Parcels
California Transportation Commission approves transfer of State land parcels to the TJPA, the City of San Francisco, and the SF Redevelopment Agency.
September 20, 2007
Winners of Design & Development Competition Announced
Pelli Clarke Pelli Architects and Hines selected as winner of the Design & Development Competition.
November 1, 2006
Design & Development Competition Launched
The TJPA launches an international competition to select a Design and Development (D/D) Team to design a Transit Center to be developed by the TJPA in downtown San Francisco and to design and develop a Tower adjacent to the Transbay Transit Center.
June 2, 2006
TJPA Board Adopts Recommended Implementation Strategy
The TJPA Board adopts a recommended implementation strategy to construct the program in two phases. Phase I includes constructing the station and the train boxes. Phase II includes the Caltrain and future high-speed rail line underground up Second Street into the new built-out train level of the station.
Recommended Implementation Strategy
January 2006
TJPA Becomes Eligible Federal Grant Recipient
August 2005
Project Receives $55 Million in Federal Funding
The Transbay Transit Center/Caltrain Extension Project receives $55 million in federal funding from the long-awaited federal surface transportation bill, SAFETEA-LU (Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users).
June 25, 2005
Redevelopment Agency Adopts Transbay Redevelopment Plan
Redevelopment Agency adopts Transbay Redevelopment Plan.
June 21, 2005
Board of Supervisors Adopts Transbay Redevelopment Plan
The Redevelopment Plan for the Transbay Terminal Project is adopted by the San Francisco Board of Supervisors. The Redevelopment Plan will transform the area surrounding the new station and create a new Transbay neighborhood with homes, parks and retail.
February 8, 2005
Preliminary Engineering Work Begins
Federal Transit Administration issues Record of Decision (ROD), confirming that the Transbay Terminal Project has satisfied all of the requirements of the National Environmental Policy Act of 1969 (NEPA) and completed the extensive federal environmental review process.
Record of Decision: Issued February 8, 2005
Appendix A: Mitigation Monitoring Program
Appendix B: Memorandum of Agreement with FTA and State Historic Preservation Officer (SHPO)
Appendix C: Summary of Public Comment
Appendix D: Executed Project Development Agreement
February 2005
Preliminary Engineering Work Begins
The TJPA begins preliminary engineering work on the Transbay Terminal Project.
2010-Present
Late 2017
Phase I of Project Completed
Construction of the new Transbay Transit Center is scheduled to be complete in 2017, creating a new, 1 million square foot Transit Center with above-grade bus level, ground floor and concourse-level retail and foundations for two below-grade levels to serve Caltrain and future high-speed rail service to Los Angeles.
January 2015
Mello Roos Community Facilities District Formed
Mayor Ed Lee signs into law legislation that creates a Mello Roos Community Facilities District (CFD) for the Transit Center District Plan (TCDP) area, which surrounds the new Transit Center. Developers choosing to upzone in the TCDP area must pay a special CFD tax to fund infrastructure needed to support upzoned (i.e. taller) buildings. The CFD represents a major new funding source for the Transbay Transit Center Program.
November 2014
Steel Assembly Begins
Bringing together thousands of steel elements manufactured and shopped at locations throughout the United States, assembly of the Transit Center’s steel superstructure begins in November 2014. The iconic Transbay Transit Center begins to take shape above ground.
October 2014
Foundation Work Completed
The foundation of the Transbay Transit Center is completed just 6 years after groundbreaking. The entire 5-foot thick, 4-block long mat slab foundation of the Transit Center is poured in an impressive 13 months.
July 2014
Bus Ramp Construction Begins
Work on the Transbay Transit Center’s new designated Bus Ramp begins with the demolition of existing footings. When complete, the ramp will connect the Transit Center directly to the Bay Bridge, keeping Transbay buses off busy downtown streets, improving bus commute times, and reducing traffic congestion.
February 2014
Excavation Work Completed
After two years of work, excavation for the Transbay Transit Center is complete. A total of 640,000 cubic yards of material from digging, trenching and preparation for foundation is removed and leads to the discovery of numerous artifacts, including the tooth of an approximately 12,000 year old Columbian mammoth.
September 2013
First Concrete Pour for Permanent Foundation
First concrete is poured for the permanent foundation for the new facility. The 5-foot thick cement foundation requires 60,000 cubic yards of concrete to cover the excavation. The foundation is poured in 15 segments, each of which requires approximately 4,000 cubic yards of concrete.
August 2012
Transit Center District Plan Enacted
The Transit Center District Plan is enacted by the City of San Francisco in order to allow upzoning of certain land parcels in the area surrounding the new Transbay Transit Center and to generate revenues to fund infrastructure in the Transbay neighborhood, including substantial revenues for the Transbay Program.
July 2012
Governor Jerry Brown Signs Historic High Speed Rail Legislation at Transbay Site
At an event on the Transbay construction site, Governor Brown signs high-speed rail legislation that will create thousands of new jobs in California by providing $8 billion in funding from Prop 1A for construction of the first segment of high-speed rail and infrastructure upgrades on the Northern and Southern “bookends” in San Francisco and Los Angeles. This includes crucial funding to complete the electrification of Caltrain, which will ultimately serve to bring high speed-rail and Caltrain into the new Transbay Transit Center.
September 2011
Completion of Demolition of Former Transbay Terminal
Demolition phase of the Transit Center is completed on time and on budget. Demolition entailed nearly 55,000 hours of labor, all of which were completed without accident or injury. Approximately 88 percent of this work was completed using local labor who worked diligently to recycle more than 7,500 tons of steel and 92,000 cubic yards of concrete—enough to fill 28 Olympic size swimming pools.
Fall 2010
Demolition of East Loop (Phase II of Temporary Terminal) Completed
The second phase of the Temporary Terminal construction begins following demolition of the east loop over the Temporary Terminal site. The removal of this outdated bus ramp allows construction of the Temporary Terminal to be completed and demolition of the Transbay Terminal to begin.
Fall 2010 – Spring 2011
Demolition of Existing Ramps and Transbay Terminal
August 2010
Demolition of the Transbay Terminal
Begin demolition of Transbay Terminal. Begin construction of Phase I of the project, including the Transit Center building and Train Box.
August 2010
Construction of Temporary Terminal (Phase I of Temporary Terminal) completed.
Temporary Terminal opens.
2010 - 2017
Construction of the new Transbay Transit Center